Phases of a Belgian construction project

Hemma organises a Belgian construction project into 12 phases. These phases come from the standard Belgian new-build sequence — not invented by Hemma, but the actual order contractors and architects expect work to happen.

01The 12 phases

#PhaseWhat it covers
0Preparation & DesignPlanning, permits, choosing an architect, soil surveys
1Earthworks & FoundationExcavation, foundations, drainage
2Structural shellWalls, floors, structural elements
3RoofingRoof structure, waterproofing, gutters
4Exterior joineryWindows, exterior doors
5Rough-in MEPElectricity, plumbing, HVAC rough-in
6ScreedFloor screed
7PlasteringInterior plaster and finishing
8FlooringFloor finishes
9FinishingPainting, fixtures, kitchen, interior doors
10Outdoor worksTerrace, driveway, garden
11Handover & AdministrationFinal inspection, EPA certificate, administrative close

02Where to see your phases

Open the Project Room. On a computer, every phase is listed down the left with where it stands in words — Done, Now · 7 of 10 milestones or Not started — and the phase you pick opens beside it. The room opens on the phase your build is in. On a phone, the room is the list of phases: tap one to open its own page, and Project Room at the top takes you back.

A phase shows how many of its milestones are completed, never a percentage of the build: milestones are what Hemma can actually see happen.

03When a phase should end

Each phase shows a Planned end. Until you set one it says Not planned yet: Hemma never works out an end date from the phase's estimated duration, because that is a guess and a guessed date looks like a promise. Choose Add a date, pick the day and choose Save. To move it, choose Change; to clear it, choose Change and then Remove the date. The day also shows in the calendar's Phases lane. See your project calendar.

04How phases move

A phase can be in one of three states:

  • Inactive — not yet started. The start conditions have not been met.
  • Active — underway. The start conditions are met but it is not yet done.
  • Done — all required milestones are complete.

Phases unlock in order. Phase 1 starts when the right milestones in Phase 0 are done. Phase 2 starts when Phase 1's conditions are met. Hemma updates this automatically as milestones complete.

05What "active" means in practice

Multiple phases can be active at the same time. In a real build, roofing, exterior joinery, and rough-in MEP often overlap. Hemma reflects that — it tracks which phases are active based on what has actually happened, not a rigid one-at-a-time sequence.

06Phases and your project type

Hemma applies a construction template when you set up your project. A new build gets all 12 phases. A renovation or extension might start later in the sequence. The template sets the initial phase structure — you can see it in the Project Room and adjust each phase with Edit.

07Common questions

Can I add my own phases? Not yet. The 12-phase structure follows the Belgian standard. You can add custom milestones and decisions inside each phase.

A phase is stuck. How do I move it forward? Phases are driven by milestones. Open the phase in the Project Room, find the blocking milestone under Still to happen and either complete it manually or check why it has not auto-completed. See milestones — what completes automatically and what doesn't.

What if my build skips a phase entirely? You can mark all milestones in that phase as done manually. The phase will move to "done" and the next phase will become active.